Zooming in the Risk-Return Matrix

If the Risk-Return Matrix contains a large number of data points, the display can get confusing. In these cases, use the zoom function to enlarge a section of the matrix.

To zoom in:

  1. Click in the Risk-Return Matrix.

  2. Hold down the mouse button and drag the selection rectangle that appears to the required size, and then click to enlarge the section.
    risk_matrix_zoom_EN.png
    This zooms into the selected area of the matrix.

  3. If necessary, repeat the zooming steps until you get the optimal display.